The budget for the Malaysian component is spelled out in the table below at output and sub-outcome levels. The indicative total budget allocation requested from GEF will be USD880,000 with a co-funding totalling to USD1,380,457 (see Table 1 below). The outputs with their respective activities are to be implemented over 4 years starting from 2010.
|
Table 1: Revised Budget For Malaysian Component
REVISED ACTIVITIES
|
REVISED GEF
|
REVISED CO-FUNDING
|
REVISED TOTAL
|
|
|
COMPONENT SUB-OUTCOME 1: Capacity and institutional framework for sustainable peatland management in Malaysia strengthened
|
|
|
|
|
Output 1.1: Policy and planning framework for peatland management strengthened at national level
|
$105,000
|
$169,000
|
$274,000
|
|
Output 1.2: Capacity for sustainable peatland management in Selangor State strengthened to support the up-scaling of good peatland management practices
|
$67,000
|
$83,000
|
$150,000
|
|
Output 1.3: Pilot site (North Selangor PSF) established as a focus for educational and awareness activities for the public.
|
$19,000
|
$195,000
|
$214,000
|
|
Output 1.4: Component technically supported
|
$49,000
|
$20,000
|
$69,000
|
|
SUB-TOTAL SUB-OUTCOME 1
|
$240,000
|
$467,000
|
$707,000
|
|
COMPONENT SUB-OUTCOME 2: The degradation of peatlands in Malaysia due to fires minimised
|
|
|
|
|
Output 2.1: Status and trends of Malaysian peatlands determined.
|
$125,000
|
$189,000
|
$314,000
|
|
Output 2.2: Degradation of peatlands by fire in Selangor State reduced.
|
$80,000
|
$157,000
|
$237,000
|
|
Output 2.3: Guidelines for integrated peatland management in Malaysia developed and promoted.
|
$57,000
|
$75,000
|
$132,000
|
|
SUB-TOTAL SUB-OUTCOME 2
|
$262,000
|
$421,000
|
$683,000
|
|
COMPONENT SUB-OUTCOME 3: Best management practices at selected demonstration sites identified and practised
|
|
|
|
|
Output 3.1: Sustainable management options for peatlands showcased through demonstration sites.
|
$141,600
|
$25,000
|
$166,600
|
|
Output 3.2: Integrated management strategies for North Selangor PSF and buffer zone adopted.
|
$40,000
|
$210,757
|
$250,757
|
|
Output 3.3: Rehabilitation of degraded peat swamp forest demonstrated in Raja Musa F.R and adjacent buffer zone.
|
$90,000
|
$96,700
|
$186,700
|
|
SUB-TOTAL SUB-OUTCOME 3
|
$271,600
|
$332,457
|
$604,057
|
|
COMPONENT SUB-OUTCOME 4: Guidelines for selected sectors relating to peatland management prepared and adopted
|
|
|
|
|
Output 4.1: Sustainable economic activities in buffer zone of NSPSF enhanced.
|
$80,000
|
$130,000
|
$210,000
|
|
SUB-TOTAL SUB-OUTCOME 4
|
$80,000
|
$130,000
|
$210,000
|
|
Total Sub-Outcome
|
$853,600
|
$1,350,457
|
$2,204,057
|
|
Project Administration & Support 3%
|
$26,400
|
$30,000
|
$56,400
|
|
TOTAL PROJECT COSTS
|
$880,000
|
$1,380,457
|
$2,260,457
|
|
| |
|